Got something to say or just want fewer pesky ads? Join us... 😊

[Misc] Building project advice



Perkino

Well-known member
Dec 11, 2009
5,978
I'd like to have an extension to my house. I would like this to be completed in the summer of 2020 and am aware I need planning permission and various contracts will need to be signed.

What I'd like to know is how far in advance I should begin to plan such a project with an architect or builder...

Also what is an expected % of cost to be paid upfront/ on completion of a big extension project estimated to cost around £70,000
 

mwrpoole

Well-known member
Sep 10, 2010
1,504
Sevenoaks
I recently had an extension and the whole project took about 2 years. 6 months to get architect, drawings, planning permission and building regs and builder. We had to wait 12 months for builder, build took 6 months. I hadn’t considered builder couldn’t start for 12 months. We had other options that could have started 6-12 months but opted for the builder we preferred and had good references for. We had a 8 part payment plan - 12.5% on day 1, then same every 4 weeks thereafter x 6 and then balance on completion. Total build was around £150k. As it worked out our build was done March - September which worked out much better than a winter build, just a consideration if knocking down walls and having roof alterations.
 

Hendrax

Well-known member
Jan 23, 2013
3,459
Worthing
No harm in starting now. Contact an architect, get the plans drawn up then submit them to the council. That'll give you plenty of time to get half a dozen quotes in.

All building companies vary. Could be a small upfront cost/deposit. Then it would be stage payments from my experience.

Ground work done: pay x amount.
Brick work up: pay x amount.

And you should definitely look at a retention plan in the contract so at the end of the project you hold on to a certain % for 3-6 months to iron out any comications, if any, that occur once the project is completed.
 
Last edited:

Weststander

Well-known member
NSC Licker Extraordinaire
Aug 25, 2011
63,156
Withdean area
We did a similar project, but luckily through a trusted family connection.

There’s no need to pay a large upfront sum, but you will need to give the contractor regular payments as they are constantly paying subbies and suppliers.

With our large home project before that one, with another contractor, I took advice from a project manager friend and ensured that that the winning contractor was willing to sign a JCT contract.
https://www.jctltd.co.uk/category/home-owner-contracts
This irrevocably set the price, staged payments and retention whilst snagging was cleared. It was linked to very detailed data spec sheets covering everything from exaxt number and location of elec fittings, insulation products/depth etc. Well worth the time and tiny cost, especially when the contractor tried to trick us over shortcuts made and unresolved errors.
 

sully

Dunscouting
Jul 7, 2003
7,823
Worthing
We did a similar project, but luckily through a trusted family connection.

There’s no need to pay a large upfront sum, but you will need to give the contractor regular payments as they are constantly paying subbies and suppliers.

With our large home project before that one, with another contractor, I took advice from a project manager friend and ensured that that the winning contractor was willing to sign a JCT contract.
https://www.jctltd.co.uk/category/home-owner-contracts
This irrevocably set the price, staged payments and retention whilst snagging was cleared. It was linked to very detailed data spec sheets covering everything from exaxt number and location of elec fittings, insulation products/depth etc. Well worth the time and tiny cost, especially when the contractor tried to trick us over shortcuts made and unresolved errors.

Good advice, but no contract has an irrevocably fixed price as that wouldn’t allow you to change your mind!

When I used the homeowner contract, I had to explain to the builder that it protected him more than me. His starting position was “I don’t use contracts”.

Some of the most important things to have in the contract are working hours, access and making good afterwards (the garden, fences, etc).

Don’t forget your architect / designer will want paying long before the builder starts.
 


Weststander

Well-known member
NSC Licker Extraordinaire
Aug 25, 2011
63,156
Withdean area
Good advice, but no contract has an irrevocably fixed price as that wouldn’t allow you to change your mind!

When I used the homeowner contract, I had to explain to the builder that it protected him more than me. His starting position was “I don’t use contracts”.

Some of the most important things to have in the contract are working hours, access and making good afterwards (the garden, fences, etc).

Don’t forget your architect / designer will want paying long before the builder starts.

The price is irrecoverably fixed. Protecting the home owner too.

Variations of work and spec either way, outside of the JCT, are obviously out of the JCT fixed price and can considerably increase the cost. The trick is to thoroughly create the spec before you go to contractors, working with an excellent architect, project manager or someone similar with extensive building knowledge.

Another advantage of a JCT is that it can set deadlines. Many busy builders in SE England take on too much work and 'spin plate', not coming clean as to the real reasons for the long absences from your job. Often a great start is made on the work, the bulk of money paid over, then a vacuum.
 

Superphil

Dismember
Jul 7, 2003
25,387
In a pile of football shirts
[MENTION=343]Eggman[/MENTION] ?
 


ofco8

Well-known member
May 18, 2007
2,386
Brighton
As a Building Estimator/Quantity Surveyor all my life I have always told householders when I visit them for pricing purposes " If our quote is not the one you want to use promise me you will NOT pay your proposed builder any money up front. If they ask for same they are not a trustworthy builder, possibly got cash flow problems. Only pay in completed stages payments."

I despair how many I have seen who ignored this advice and then "cry" when the builder goes bust or just walks away with their money.
 

Bold Seagull

strong and stable with me, or...
Mar 18, 2010
29,716
Hove
The price is irrecoverably fixed. Protecting the home owner too.

Variations of work and spec either way, outside of the JCT, are obviously out of the JCT fixed price and can considerably increase the cost. The trick is to thoroughly create the spec before you go to contractors, working with an excellent architect, project manager or someone similar with extensive building knowledge.

Another advantage of a JCT is that it can set deadlines. Many busy builders in SE England take on too much work and 'spin plate', not coming clean as to the real reasons for the long absences from your job. Often a great start is made on the work, the bulk of money paid over, then a vacuum.

JCT homeowner contracts, like all JCTs do allow for variation of the contract works. These shouldn't considerably increase the cost and should only reflect the cost of that work. If you therefore wanted to add a wall, or change a layout, the contract allows for the Employer to request that, and the Contractor to provide a reasonable price based on his initial costings of the job. If they priced £4000 for 10 meters of partitions and you add 2m, then the cost should be around £800, plus any work that might be required to effect that change. In the Homeowner Contracts I think this is covered in Condition 5.

I agree with you though, I wouldn't trust any builder not prepared to enter into an approved contract, especially a JCT Homeowner which is basic, clearly written with limited legal jargon. Any project over £100k I would be looking at a JCT Minor Works Contract as this is more robust, and is more clear on how variations are dealt with. If penalties for late finishing need to be introduced, say you had a rent while works went ahead, then you'd have to consider the JCT Intermediate Contract that allows you to set Liquid and Ascertained Damages for late finishing by the contractor, although conversely the Contractor is entitled to an Extension of Time and to claim Prelims if they are delayed by variations for the contract, unforeseen circumstances from the existing building, severe weather etc.

What is always important is to ensure as the Employer that you are not ahead of the works undertaken with your payments, and the value of the works to each point has 5% held back for the retention. For the MW and IC contracts gaps in work progressing on site are a breach of contract and can lead to determination of the contract by the Employer.

You should allow around 15% for consultants (architect/QS - full service, structural engineer) and local authority fees. A budget of £100,000 would break down something like this:
Consultants fees and application charges: £15,000
Contract sum: £65,000
10% Contingency: £ 6,500
VAT: £14,300
 


mothy

Well-known member
Dec 30, 2012
2,093
I recently had an extension and the whole project took about 2 years. 6 months to get architect, drawings, planning permission and building regs and builder. We had to wait 12 months for builder, build took 6 months. I hadn’t considered builder couldn’t start for 12 months. We had other options that could have started 6-12 months but opted for the builder we preferred and had good references for. We had a 8 part payment plan - 12.5% on day 1, then same every 4 weeks thereafter x 6 and then balance on completion. Total build was around £150k. As it worked out our build was done March - September which worked out much better than a winter build, just a consideration if knocking down walls and having roof alterations.

Pretty much this for me too. 6 months to planning approval, 6 month wait for builder & 6 months build & to final finishes
 

Triggaaar

Well-known member
Oct 24, 2005
49,900
Goldstone
I'd like to have an extension to my house. I would like this to be completed in the summer of 2020 and am aware I need planning permission and various contracts will need to be signed.

What I'd like to know is how far in advance I should begin to plan such a project with an architect or builder...
If there's any chance PP will be rejected, but passed on appeal, you'll need to get going a couple of years early.
 

Weststander

Well-known member
NSC Licker Extraordinaire
Aug 25, 2011
63,156
Withdean area


Justice

Dangerous Idiot
Jun 21, 2012
18,180
Born In Shoreham
As a Building Estimator/Quantity Surveyor all my life I have always told householders when I visit them for pricing purposes " If our quote is not the one you want to use promise me you will NOT pay your proposed builder any money up front. If they ask for same they are not a trustworthy builder, possibly got cash flow problems. Only pay in completed stages payments."

I despair how many I have seen who ignored this advice and then "cry" when the builder goes bust or just walks away with their money.
Ha people that have never been on the tools always come out with this rubbish. We always take a deposit prior to start date and if the client disagrees which is never to be honest then I would walk away.
 

portslade seagull

Well-known member
Jul 19, 2003
17,580
portslade
Just had one done took around 15months from start to finish. Planning approval is the balls ache. We set 90k but with extras and unforeseens it came in around 110k. Still have odds and sods to do
 

Perkino

Well-known member
Dec 11, 2009
5,978
Just had one done took around 15months from start to finish. Planning approval is the balls ache. We set 90k but with extras and unforeseens it came in around 110k. Still have odds and sods to do

Can I ask about the size of the building work and the reason that planning wasn't approved initially
 

portslade seagull

Well-known member
Jul 19, 2003
17,580
portslade
Can I ask about the size of the building work and the reason that planning wasn't approved initially

Mine was a single storey extension and there were issues with the roof and footings. They were mutually sorted in the end but if rejected like ours the hoops multiply. With the footings we had to concrete in an RSJ.
 


Perkino

Well-known member
Dec 11, 2009
5,978
Mine was a single storey extension and there were issues with the roof and footings. They were mutually sorted in the end but if rejected like ours the hoops multiply. With the footings we had to concrete in an RSJ.

90k for a single storey extension is quite a lot
 

Live by the sea

Well-known member
Oct 21, 2016
4,718
Have a fair bit of experience in this field . Firstly it is often more cost effective, quicker and less stressful to employ a building firm that manages the whole process, this way you don’t need to employ a separate architect who has no real interest in the build or whether it meets your budget , they just want to get paid for producing the drawings.

Secondly always pay in stages as the work progresses and allow 15% extra for things that may or may may not come up during the build

As a ballpark a decent firm will charge you around £1900 a square metre to build but that’s for a straight forward new build, moving load baring walls etc and extra pipe work is going to increase that price as will how much you spend on the interior. For example I know a guy who wanted a big glass vaulted ceiling on his single story extension which was about 30 feet by 25 ft rather than the cheaper options and the quote for the vaulted ceiling came back at £85,000. So depends really how far you want to go to create the look and how big your budget is. He had already budgeted £40,000 for the kitchen so wanted a cool looking roof as well.
 
Last edited:

Albion and Premier League latest from Sky Sports

Paying the bills

Latest Discussions

Paying the bills

Paying the bills

Paying the bills


Top
Link Here